Thursday, August 28, 2008
How plumbers save the world!
The plumbers are checking and rechecking all the measurements. (And marking the floor again) Tentatively set to cut the floor on tuesday.
Tuesday, August 26, 2008
Equipment Starts to arrive
Monday, August 25, 2008
Equipment Package
Met with the equipment supplier this morning. First thing he did was measure all of the doors to figure out how he would stage and unload everything. That is why I like to work with people smarter than me as I am not sure I would have started there. After a few measurements we seem to be all clear.
Friday, August 22, 2008
Bldg Permit in hand!
After a few computer related glitches held us up yesterday, the GC went downtown and straightened everything out. Really wasn't a big deal as everyone had signed off that needed to but the computer that releases the permit was still spitting out not approved.
Thursday, August 21, 2008
Wednesday, August 20, 2008
What color is your floor?
Meet with GC and floor company regarding the dinning room floor and the kitchen floor. Going with a stained floor in the dining room and a quartz granule for the kitchen floor. Many different colors to choose from. We have several we like and they tell us where we can see jobs in Durham with the same color. So in the next few days if you see me walking around area restaurants looking at floors, you will know what I am up to.
Monday, August 18, 2008
24
Got the feedback from the health department review. 24 items that they need clarification, more information, or outright changed. GC and I huddle and craft a response. Took the health departments' serv safe class last week, many of the items he pointed out were part of that class so our response doesn't take long. Now we wait for final building permit. Hopefully in the next day or so. Plumbers would like to get started on friday.
Friday, August 15, 2008
Almost There.....
8/15/2008
Plan Review Update for Green Tango at Pavilion East:
Building: OK 8/15/2008
Planning: OK 8/13/2008
Plumbing: OK 8/01/2008
Fire Prevention: OK 8/11/2008
Electrical: OK 8/6/2008
Mechanical: Not Reviewed as of 8/15/2008
Health Department: Not Reviewed as of 8/15/2008
Plan Review Update for Green Tango at Pavilion East:
Building: OK 8/15/2008
Planning: OK 8/13/2008
Plumbing: OK 8/01/2008
Fire Prevention: OK 8/11/2008
Electrical: OK 8/6/2008
Mechanical: Not Reviewed as of 8/15/2008
Health Department: Not Reviewed as of 8/15/2008
Thursday, August 14, 2008
Monday, August 11, 2008
Power Is On!
After a brief tour through the city inspections department (almost a blog unto itself), Duke Power has thrown the switch.
Thursday, August 7, 2008
Wednesday, August 6, 2008
Health Deptartment Plan review
Tuesday, August 5, 2008
Health Department Plan Review
Picked up another set of plans this afternoon for the health department review. Will submit tomorrow morning. Hopefully our work last month with the health department will make for a smooth plan review.
Friday, August 1, 2008
some caveat/contingencies...
reviewing the sprinkler work to be done. The as-builts for sprinkler system may be bigger than our whole plan. yikes. Seems to be a good guy bidding the work. nice but honest about where the problems may be.