Tuesday, September 30, 2008
Bulkhead Day 2
Work continued today on the bulkhead. Thought we would have to move the ceiling to get the bulkhead in, but they worked around it and did not have to take it down. Just meant that the guy pushing the scaffolding had to move it about a thousand times. Shame I didn't have time lapse photography of him working.
Monday, September 29, 2008
Framing the Bulkhead
Work began today framing the bulkhead that runs over our counter. As the work was being laid out the GC realized that the bulkhead was in conflict with the kitchen door. None of us realized this in earlier reviews (including the architect who drew it). GC figures that it would be important for the door to open. So we moved it by 3 inches. For those keeping score it is now 7 foot 3 rather than a straight up 7 foot.
Friday, September 26, 2008
Framing, Part Deux
Thursday, September 25, 2008
Tuesday, September 23, 2008
Georgia Buggy
Learned late yesterday that the concrete truck would not be allowed to pull up in front of the space. Landlord was concerned that the weight would damage their parking lot. So we had to order Georgia Buggys. Basically an atv like vehicle that you can fill with concrete and drive onto the site to pour. Took a little more time (and money) but went smoothly.
Monday, September 22, 2008
Friday, September 19, 2008
Brute
Today the plumbers finished installing all of the lines and prepared for inspections on monday. They packed up brute shortly after this picture was taken. Don't think I have ever seen a more aptly named piece of equipment.
Thursday, September 18, 2008
Plumbers back at work this morning very early (pre 6AM) so that they could tie our lines in to building lines. Everything went smoothly and they plan for first plumbing inspection on Monday.
Wednesday, September 17, 2008
Louver two, electric boogaloo
Louver rears its head again, as the hvac contractor notes the presence of several drains lines that cross right in front of our opening. Hard to tell from the ground but on the ladder it is easy to see why the lines may need to be moved so that our hvac work can make the required drop per foot and still exit out the louver. In discussions with multiple people about how to get this done and who's responsibility it may be. GC is invaluable at navigating complex arrangements such as these.
Tuesday, September 16, 2008
Transformer in the sky
Some time ago we identified that the transformer needed to be moved (as it was mostly blocking the back door)and today was the day the electrician moved it. Missed seeing the lift that got it up there (as the transformer weighs well over 300 lbs) Should give us a little more space to work with during construction and beyond.
Plumbers return to save the world tomorrow.
Friday, September 5, 2008
Some things are more important
GC had to leave town unexpectedly because of a death in the family. Sometimes you just have to roll with those things you cannot control.
Agreed that it was best to put everything on hold till he returned sometime next week. Would rather stop and make sure we did everything right than push ahead and make a mistake.
Will give us a little time to sort out an engineering issue that has been bubbling just below the surface (literally) for the past few days. Basically the plumbers can't finish tying in the main line because the line the engineers specified is not in the place that was listed on the as builts. Or it is there and not exactly in the right place. Bottom line the engineer has to go back to the drawing board and figure out this all out by the time the GC returns.
Agreed that it was best to put everything on hold till he returned sometime next week. Would rather stop and make sure we did everything right than push ahead and make a mistake.
Will give us a little time to sort out an engineering issue that has been bubbling just below the surface (literally) for the past few days. Basically the plumbers can't finish tying in the main line because the line the engineers specified is not in the place that was listed on the as builts. Or it is there and not exactly in the right place. Bottom line the engineer has to go back to the drawing board and figure out this all out by the time the GC returns.
Thursday, September 4, 2008
Core Drilling
Plumbers returned today to core drill our floor sinks for what will be our dish room. The back of Green Tango Pavilion East is not on a slab, so there is no digging. If you look through the hole you can see a cage below that contains a residential tenants belongings. The guys didn't put down plastic before they drilled so the cage received a fine coating of dust. The building management was none too happy (rightfully so) but I think we sorted everything out by the end of the day.
Looking through the hole into the cage makes me think of a crime caper like Oceans Eleven or The Italian Job.
Wednesday, September 3, 2008
Dig it
Tuesday, September 2, 2008
In ancient times, hundreds of years before the dawn of history, an ancient race of people... the Druids.
Early Morning Ceiling Tiles
Subscribe to:
Posts (Atom)
Twitter Updates
Pavilion East Links
Blog Archive
-
▼
2008
(92)
-
▼
September
(15)
- Bulkhead Day 2
- Framing the Bulkhead
- Framing, Part Deux
- Framing
- Georgia Buggy
- Plumbing Inspection
- Brute
- The Big Dig
- Louver two, electric boogaloo
- Transformer in the sky
- Some things are more important
- Core Drilling
- Dig it
- In ancient times, hundreds of years before the daw...
- Early Morning Ceiling Tiles
-
▼
September
(15)