Monday, December 22, 2008
Sunday, December 21, 2008
Saturday, December 20, 2008
Friday, December 19, 2008
Permisiion is granted to operate a...
Restaurant! We passed and received our permit from the health department. We came in just under the wire. We were putting the finishing touches on everything as the inspector was walking across the parking lot.
GC summed everything up (as only he can) "Now the real work begins." Soft opening is scheduled for monday.
Thursday, December 18, 2008
Pre Opening Visit - 9 More Things
Glass for the sneeze guard was installed this morning. Health Inspector came by for a pre-opening visit this afternoon. Left with 9 things that needed to be addressed before we can get our permit and open. Inspector will be back late on friday afternoon. We have less than 24 hours to handle all 9 things or we most likely will not be permited till January. Going huddle with the GC and see if we can make it.
Friday, December 12, 2008
Close....to losing my mind
Sneeze guard is in, but alas no glass. Same company who made the mistakes with the sink that I wrote about previously decided to cut the wrong glass as well. First time I have ever asked anyone to leave a job, but felt that given their track record we were better off going with another company. We had hoped to be open already but can't without the glass. Local company is going to rush it but even with that still about a week a way.
Thursday, December 11, 2008
Failed Plumbing Inspection
Monday, December 8, 2008
What did you think you were doing today?
Hit a little bit of a roadblock late on friday. An unamed supplier royally screwed up the dimensions of our dish sink. Unbeknownst to everyone involved he decided to make his own sink rather than the one we ordered.
In addition they showed up with no tools to break it down (so that it would fit through the door) and no crew to actually move it in. Fortunanetly the GC saved the day with both the tools and the crew. Which was no small feet considering it was Friday afternoon at 4PM. Most construction sites are a ghost town by that point.
Friday, December 5, 2008
New Menu Boards
Thursday, December 4, 2008
Wednesday, December 3, 2008
Getting it Right
Tuesday, December 2, 2008
Stacked
Monday, December 1, 2008
Hanging Signs
Wednesday, November 26, 2008
Tuesday, November 25, 2008
Polishing Corian
Corian Instillation started today. A lot of the work they were able to do off site (the cutting and forming of the individual pieces). The pieces fit together like a giant puzzle and then they came back and sanded and polished the edges together to make smooth surfaces. All the sides were done today and tomorrow they will be back to make the tops (with the cutting board inserts).
Monday, November 24, 2008
That's a straight line
Sunday, November 23, 2008
Blocks!
Now that the cabinets are in the GC and woodworker? woodsmith? carpenter?(not sure what he calls himself although I would be happy to call him the man based on his work) have begun work on our logo blocks that adorn the wall. The GC spent the weekend sketching out the plans, making adjustments and ordering the boards. One of my favorite parts of the original Green Tango design (thanks john!)
Saturday, November 22, 2008
Friday, November 21, 2008
Taking Photos of Photos
Thursday, November 20, 2008
You always forget something
Wednesday, November 19, 2008
Green Tango Application for Employment
With opening day near Green Tango is now hiring.
Green Tango Application
Questions? email info@greentango.com
Green Tango Application
Questions? email info@greentango.com
Saturday, November 15, 2008
Paint
Friday, November 14, 2008
Menu Boards
Thursday, November 13, 2008
Floor Preperations
Tuesday, November 11, 2008
Monday, November 10, 2008
Little Drawings
Friday, November 7, 2008
Here Comes the FRP (Fiberglass Reinforced Plastic)
Thursday, November 6, 2008
Progress through Puzzles
Walk-In Cooler was delivered and installed today. Surprisingly smooth process. They apparently fabricate and put together in a warehouse to make sure it works. Then disassemble and send to the site. It is not stick tab A into slot B, but not much more complicated than that. The Walk in is the workhorse of our operation because of the amount of produce we handle, so we went for the model with no interior drain lines or condensers. Buys us a few extra feet of storage which at 1500 sq ft is important.
Monday, November 3, 2008
Drywall
Friday, October 31, 2008
Cutting Steel
One aspect of the construction process that I haven't been able to capture is how noisy it can be. Think that this clip adequately does that. One of the few times that I saw the HVAC guys working less than 15 feet off the ground.
Thursday, October 30, 2008
Steel In Plastic
Wednesday, October 22, 2008
Trapdoor
Tuesday, October 21, 2008
Oh, now I am a gardner too?
Monday, October 20, 2008
What Color is your floor?
Friday, October 17, 2008
Waiting for Coke
Thursday, October 16, 2008
Wednesday, October 15, 2008
15 ladders = A lot of standing around
Tuesday, October 7, 2008
March of The Tin Soliders
Friday, October 3, 2008
Columns
This column had been hanging around in the back room since construction started. Basically it is one of the rails to the Elevator in the breezeway. It penetrates the two hour wall into our space. There was some question as to what should happen to it (and ultimately who would be responsible for it) but the inspector ruled this week that it would have to be wraped in three layers of sheet rock.
Tuesday, September 30, 2008
Bulkhead Day 2
Work continued today on the bulkhead. Thought we would have to move the ceiling to get the bulkhead in, but they worked around it and did not have to take it down. Just meant that the guy pushing the scaffolding had to move it about a thousand times. Shame I didn't have time lapse photography of him working.
Monday, September 29, 2008
Framing the Bulkhead
Work began today framing the bulkhead that runs over our counter. As the work was being laid out the GC realized that the bulkhead was in conflict with the kitchen door. None of us realized this in earlier reviews (including the architect who drew it). GC figures that it would be important for the door to open. So we moved it by 3 inches. For those keeping score it is now 7 foot 3 rather than a straight up 7 foot.
Friday, September 26, 2008
Framing, Part Deux
Thursday, September 25, 2008
Tuesday, September 23, 2008
Georgia Buggy
Learned late yesterday that the concrete truck would not be allowed to pull up in front of the space. Landlord was concerned that the weight would damage their parking lot. So we had to order Georgia Buggys. Basically an atv like vehicle that you can fill with concrete and drive onto the site to pour. Took a little more time (and money) but went smoothly.
Monday, September 22, 2008
Friday, September 19, 2008
Brute
Today the plumbers finished installing all of the lines and prepared for inspections on monday. They packed up brute shortly after this picture was taken. Don't think I have ever seen a more aptly named piece of equipment.
Thursday, September 18, 2008
Plumbers back at work this morning very early (pre 6AM) so that they could tie our lines in to building lines. Everything went smoothly and they plan for first plumbing inspection on Monday.
Wednesday, September 17, 2008
Louver two, electric boogaloo
Louver rears its head again, as the hvac contractor notes the presence of several drains lines that cross right in front of our opening. Hard to tell from the ground but on the ladder it is easy to see why the lines may need to be moved so that our hvac work can make the required drop per foot and still exit out the louver. In discussions with multiple people about how to get this done and who's responsibility it may be. GC is invaluable at navigating complex arrangements such as these.
Tuesday, September 16, 2008
Transformer in the sky
Some time ago we identified that the transformer needed to be moved (as it was mostly blocking the back door)and today was the day the electrician moved it. Missed seeing the lift that got it up there (as the transformer weighs well over 300 lbs) Should give us a little more space to work with during construction and beyond.
Plumbers return to save the world tomorrow.
Friday, September 5, 2008
Some things are more important
GC had to leave town unexpectedly because of a death in the family. Sometimes you just have to roll with those things you cannot control.
Agreed that it was best to put everything on hold till he returned sometime next week. Would rather stop and make sure we did everything right than push ahead and make a mistake.
Will give us a little time to sort out an engineering issue that has been bubbling just below the surface (literally) for the past few days. Basically the plumbers can't finish tying in the main line because the line the engineers specified is not in the place that was listed on the as builts. Or it is there and not exactly in the right place. Bottom line the engineer has to go back to the drawing board and figure out this all out by the time the GC returns.
Agreed that it was best to put everything on hold till he returned sometime next week. Would rather stop and make sure we did everything right than push ahead and make a mistake.
Will give us a little time to sort out an engineering issue that has been bubbling just below the surface (literally) for the past few days. Basically the plumbers can't finish tying in the main line because the line the engineers specified is not in the place that was listed on the as builts. Or it is there and not exactly in the right place. Bottom line the engineer has to go back to the drawing board and figure out this all out by the time the GC returns.
Thursday, September 4, 2008
Core Drilling
Plumbers returned today to core drill our floor sinks for what will be our dish room. The back of Green Tango Pavilion East is not on a slab, so there is no digging. If you look through the hole you can see a cage below that contains a residential tenants belongings. The guys didn't put down plastic before they drilled so the cage received a fine coating of dust. The building management was none too happy (rightfully so) but I think we sorted everything out by the end of the day.
Looking through the hole into the cage makes me think of a crime caper like Oceans Eleven or The Italian Job.
Wednesday, September 3, 2008
Dig it
Tuesday, September 2, 2008
In ancient times, hundreds of years before the dawn of history, an ancient race of people... the Druids.
Early Morning Ceiling Tiles
Subscribe to:
Posts (Atom)
Twitter Updates
Pavilion East Links
Blog Archive
-
▼
2008
(92)
-
►
November
(16)
- Day 2 of the Corian
- Polishing Corian
- That's a straight line
- Blocks!
- First Cabinet
- Taking Photos of Photos
- You always forget something
- Green Tango Application for Employment
- Paint
- Menu Boards
- Floor Preperations
- Timbre
- Little Drawings
- Here Comes the FRP (Fiberglass Reinforced Plastic)
- Progress through Puzzles
- Drywall
-
►
September
(15)
- Bulkhead Day 2
- Framing the Bulkhead
- Framing, Part Deux
- Framing
- Georgia Buggy
- Plumbing Inspection
- Brute
- The Big Dig
- Louver two, electric boogaloo
- Transformer in the sky
- Some things are more important
- Core Drilling
- Dig it
- In ancient times, hundreds of years before the daw...
- Early Morning Ceiling Tiles
-
►
November
(16)