Thursday, August 28, 2008

How plumbers save the world!


The plumbers are checking and rechecking all the measurements. (And marking the floor again) Tentatively set to cut the floor on tuesday.

Tuesday, August 26, 2008

Equipment Starts to arrive



Ceiling Tiles will have to come down first. And then we will have to figure out a place to store them so they do not get broken.

Monday, August 25, 2008

Equipment Package

Met with the equipment supplier this morning. First thing he did was measure all of the doors to figure out how he would stage and unload everything. That is why I like to work with people smarter than me as I am not sure I would have started there. After a few measurements we seem to be all clear.

Friday, August 22, 2008

Bldg Permit in hand!

After a few computer related glitches held us up yesterday, the GC went downtown and straightened everything out. Really wasn't a big deal as everyone had signed off that needed to but the computer that releases the permit was still spitting out not approved.

Thursday, August 21, 2008

Wednesday, August 20, 2008

What color is your floor?

Meet with GC and floor company regarding the dinning room floor and the kitchen floor. Going with a stained floor in the dining room and a quartz granule for the kitchen floor. Many different colors to choose from. We have several we like and they tell us where we can see jobs in Durham with the same color. So in the next few days if you see me walking around area restaurants looking at floors, you will know what I am up to.

Monday, August 18, 2008

24

Got the feedback from the health department review. 24 items that they need clarification, more information, or outright changed. GC and I huddle and craft a response. Took the health departments' serv safe class last week, many of the items he pointed out were part of that class so our response doesn't take long. Now we wait for final building permit. Hopefully in the next day or so. Plumbers would like to get started on friday.

Friday, August 15, 2008

Almost There.....

8/15/2008

Plan Review Update for Green Tango at Pavilion East:

Building: OK 8/15/2008
Planning: OK 8/13/2008
Plumbing: OK 8/01/2008
Fire Prevention: OK 8/11/2008
Electrical: OK 8/6/2008
Mechanical: Not Reviewed as of 8/15/2008
Health Department: Not Reviewed as of 8/15/2008

Thursday, August 14, 2008

Lines in the sand



Floor has been remeasured and marked, preparing for the first cut.

Monday, August 11, 2008

Power Is On!

After a brief tour through the city inspections department (almost a blog unto itself), Duke Power has thrown the switch.

Thursday, August 7, 2008

Wednesday, August 6, 2008

Health Deptartment Plan review



As you can see from the above plans are in, and the hand in the upper right is writing us a receipt for them.

Tuesday, August 5, 2008

Health Department Plan Review

Picked up another set of plans this afternoon for the health department review. Will submit tomorrow morning. Hopefully our work last month with the health department will make for a smooth plan review.

GC's Workbench....


has arrived. Our start is imminent, I hope.

Friday, August 1, 2008

some caveat/contingencies...

reviewing the sprinkler work to be done. The as-builts for sprinkler system may be bigger than our whole plan. yikes. Seems to be a good guy bidding the work. nice but honest about where the problems may be.