Monday, July 21, 2008

Meeting at Engineers office

This afternoon was a thorough (and I mean thorough) reveiw of basically every line on the complete drawing set. The GC, me, and the Mechanical/Electrical/ Plumbing engineers went through everything and checked and rechecked all of the details. Very time consuming but as the GC says better to find now that there is a problem than in the field. No major issues other than a few equipment questions that we were able to find the answers to.